a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

I really need help on this.
Simplify: (2.4)(a – 0.2b + 3.5c) options: A.2.4a – 0.48b + 8.4c B. 2.4a – 4.8b + 84c C. 2.4a + 2.2b + 5.9c D. 2.4a – 4.8b + 8.4c
the official ideology of a totalitarian nation is focused on creating and promoting A. communism. B. nationalism. C. exploitation. D. diversity.
You're using disk management to view primary and extended partitions on a suspect's drive. the program reports the extended partition's total size as larger tha
How many different three digit locker combinations are possible if the digits are able to repeat? 30 1000 300
Geometry math question no Guessing and Please show work thank you
Geometry math question no Guessing and Please show work
If Charlotte started doing her homework 9:15 and she finished 7 and a half hours later,what time did she finish?
What is the ordinary interest paid on a $1,600 loan if the loan is for 90 days at a 13% interest rate?
Hay muchos __________en el museo. siglo exposiciones visitantes